Category Archives: Insulation

Renovation Work

Self Build-Renovating an old house

I came across information over the years that may help the self builder when it comes to retrofits (doing up an existing dwelling).

This is probably the most challenging of self builds as the options are few when it comes to insulating a house that was never designed to be insulated.

The other problem for the self builder is how well were the houses built in the first place -are the construction details good?. If they are good then it may be an easy step (it is evident that today there are problems with new builds. Could it have been any different in the past?)-for example were the cavities clean, state of repair of pointing, brickwork etc., .

A Guide to doing it right

The document below is a very good guideline on renovating an old building correctly when it has solid walls.

a-bristolians-guide-to-solid-wall-insulation

Check for any newer versions at their web site.

I extracted a sample of the contents from the above guide by way of example.

good-practice
Solid Wall Insulation
poor-practice
Solid Wall Insulation Poor Practice

External Insulation and Cavity Wall Insulation

It is worth reading  what has gone wrong and can go wrong with this recent report below on two methods of insulation carried out on as upgrades –Post Installation Performance of Cavity Wall & External Wall Insulation.

Internal Insulation

The other method of internal wall dry lining insulation can be fully reviewed at this web site.

Top Tips from the same author above

It also needs to be realised that by adding insulation to a wall that was not designed for insulation can make the house colder if the solution is not correct, structurally damage the wall over time or cause mould on the inside that may affect your health. The above report goes through this.

Objective

The above will hopefully guide the self builder away from the problems and find the correct solution.

One needs to fully understand that one needs to choose the most robust solution that can withstand something going wrong. 

 

Possible Products 

Some of these products may be safer to use when it comes to old buildings . Some require extra measures to ensure they keep the building dry and you warm.

Diasen Thermal Plaster and its use can be seen at this link Diathonite Evolution internal wall insulation

Calsitherm Climate Board

Multipor products

TecTem from Knauf and idea on prices

Perlite

E-LINE NATURAL HYBRID

Pavadry

Foamglass

Cellulose

Rockwool

Acoustic and Fire Design

Fire and Acoustic Isolation

Having recently come across a best practice guide for Electrical installations and their effect on the fire performance of buildings I have decided to change  the approach to the fire/acoustic isolation between rooms. I will now install Rockwool flexi 50mm in the 100mm partition walls and Rockwool flexi 100mm in the 140mm partition walls .

Electrics before insulation
Partition before Insulation with Wiring
Rockwool
Partition wall with Rockwool installed

From an acoustic perspective I was advised that it is better to install the Rockwool in the centre of the partitions rather than touching one or other side of the plasterboard as this limits the sound transfer.

The Electrical Safety Council best practice guide deals with Electrical installations and their impact on the fire performance of Domestic premises at this link when one is building a home. A summary is as follows but the full document is worth reading for any self builder.

  • Fire containment in the event of a fire
  • The need to prevent fire from passing through holes in all elements whether solid or lightweight is addressed.
  • Electrical Equipment is identified that has a direct and significant influence on the fire performance of an element.
  • Partial Penetrations –those that reduce the fire performance of part of the wall/ceiling or floor.
    Full Penetrations-such as ducts and fans that go through both elements of a wall/ceiling/floor.

 

Window/Door Thermal Bridge Detail

Installation Detail

Below is the plan to deal with the window/door threshold detail to minimise thermal bridging and provide airtightness.

The window sits on a 30mm piece of Compacfoam . I used Compacfoam 200. I rebated the Compacfoam under the window so that the floor boards would fit under the window and sit on the non rebated edge.

frame mounted on compacfoam with a routed rebate
Compacfoam 30mm with rebate (Used router to rebate)

I placed 15mm Compacfoam along the lenght of the window and glued these with Orcon F.  The direction of the Compacfoam will determine the floor board direction.

compacfoam
Strips of Compacfoam

I then used 15mm Aerogel to seal around the Compacfoam. Under the window I installed the Proclima profil tape so that I could tape the Intello membrane later.

I left the centre protection tape in place on the Intello profil so that the wooden floor would go in as far as possible on the membrane.

aerogel
Aerogel 15mm

The Intello membrane was then taped ensuring that it was placed as near to the window as possible .  I taped the membrane to the floor . This finished the detail.

proclima
Proclima Solitex Plus in place

An example of the possible future wooden floor sample in place is seen below or stone/slate or marble finish.

floor board

I will first seal the floor with a product from Lakeland paint in the UK in order to minimise dust. (It looks like a very high eco specification sealer ).

I then plan to install a marble /stone slab to bridge the gap and connect this to the wooden floor.

 

 

Thermal Bridges

As part of the passive house requirement one needs to eliminate or minimise heat loss through linear lengths or points around the house. Some of the thermal bridges in my build are typical of other builds. I hope to provide more details in the future.

One of the main linear heat losses is with window/door installations (its connection with the wall frame ). It has been said numerous times that selecting a high quality window/door and installing it poorly can equate to buying a low energy window .

As mentioned before I will use the free software called Therm to calculate the losses. The first detail to tackle is the glazing which was directly mounted in the frame of the house without a window frame.  These windows are 2.4 metres x .9 metre and there are 11 of these mounted on the south face.

The calculation of these linear losses can be expensive to get done so I will be doing the task myself and have it checked by others. I am surprised that good details are hard to come by on the web for free to help the self builder. One of the most time consuming exercises with thermal bridge calculations is drawing the detail. If one undertakes drawing this oneself using CAD (Computer Aided Design) software it can help to reduce the cost of the calculation.

When one needs to come up with a detail to minimise the losses there are a lot of products that help to keep the losses under control. These are semi-rigid insulation products like compacfoam, foamglass blocks, standard insulation, TECTEM, PU or rockwool and fibreglass products and aerogels (which is one of the highest performing insulators being made).

To date there appears to be very few online resources to guide the self builder or provide details that one can use before one starts a build.

Some background and details I found to date on thermal bridges can be found at the following links.

What is a Thermal Bridge

Leeds Beckett University

Scottish Thermal Bridge Details Link

Example of Heat Loss through a glass spacer

Below is an example of the thermal bridge calculations one needs to carry out to establish the thermal bridge performance values in W/(mk).

  • One draws the detail as a DXF file using a drawing package (or draw the detail manually in Therm)
  • Import the detail into Therm Software
  • Add the technical details such as thermal conductivity of each item
  • Tell Therm where on the drawing to stop the calculation (Adiabatic)-top and bottom of the drawing shown below.
  • Tell Therm what the internal and external temperatures are
  • Go to a spreadsheet and calculate the psi values of the thermal bridge detail for the passive house performance value.

When this is done one ends up with the calculation and an image like that shown below. In this image the glass is shown near the top right.

Drawing Detail

 

In the next image the colours show the temperature gradients. The purple colour is the outside temperature at -10 degrees.

colour infrared
There is thermal bridge software that one can buy where the software calculates the psi value without using a spreadsheet but Therm is free and there are courses available in Ireland.

If one wants to show the real design and installation details of the thermal bridge values for the Irish regulations rather than the accredited details (without a performance value)  one needs to use a certified thermal bridge accessors but this is not the case for the Passive House Institute.

We can all look forward to the day when standard construction details that are typically used in Ireland are already calculated for the self builder and there will be no need to pay to find out the thermal bridge losses . The Scottish accredited details (see above link) come close to taking the guess work out of construction.

 

Window Wall Build Up

Batten and Counter Batten fixing

Below are a few images of the build-up I used around the windows. The first image shows the batten (45x40mm planed ) build up on the window wall. I tried to offset the battens around the windows so as to minimse thermal bridges. The wall battens are installed at 90 degrees to the vertical window sections behind the OSB.

Passive House Timber Frame Build Up
Insulation

The image below is the RWA45 rockwook installation before the airtight membrane was installed. The wooden strips on the window sill are there to support the sill board. I kept them away from the window frame in order to decrease the thermal bridge. I now plan to use Rockwool RWA45 on all window sills as it performs better at not absorbing water as seen on a previous blog.

Window Insulation Detail Passive House
Thermal Bridge Build Up

The next image shows the finish layer of battens over the membrane.

Passive House Window Detail
Batten Finish Detail

 

 

 

 

 

 

 

 

 

 

 

The window (below) which was installed in the structural frame of the building (I purchased the glazing without the frame 2.4mx.9m) provides light and solar gain. Small lengths of floor board OSB were cut to size in order to build up the insulation and provide a base for the plasterboard finish.

wood spacers for insulation

 

 

 

 

 

 

 

 

 

 

Insulation is placed up against the glass and I plan to place a timber bead around the edge . Plasterboard will then finish the detail.

glazing insulation for glass in structure

 

 

 

 

 

 

 

 

 

 

The finished (near finished) wall looks like this below.

Passive House Wall Detail
Window Wall Detail

Building Science and Physics

I recently came across a few videos from America on the subject of building physics. They may help the self builder when trying to figure the wall system, roof design or insulation to use.

The videos are presented by Joseph Lstiburek who outlines the do’s and dont’s in a very direct manner.  He is the founder of Building Science Corporation.

In the videos he references the American method of describing heat loss which is the R value (resistance to heat loss per inch- a higher number is better) while in Europe we mainly use the U value (ease in which heat travels through an object-a lower number is better but it includes boundary air films). The R value is the thickness of the insulation divided by the K value or in the examples  presented by Joseph Lstiburek the R value of 2 of the Irish building is approximately equivalent to a U value of 0.5.

This video starts with the progress for insulating buildings in 1000 years (starting with an Irish Church) and covers the perfect wall, roof and slab and the importance of designing buildings for the climate they are situated in.

Video  (Below)

Commercial Thermal Bridging , LEED Building Problems, Water problems.

Physics Discussed (2nd law of thermodynamics)

  • Heat flow is from warm to cold
  • Moisture flow is from warm to cold
  • Moisture flow is from more to less
  • Air flow is from a higher pressure to a lower pressure
  • Gravity acts down

Quality Assurance-Figuring out what the right thing to do is

Quality Control– Executing it

The building layer order of importance for a wall, roof and slab and the importance of continuity between the layers as shown below in order of importance.

  • Water control layer
  • Air control layer
  • Vapour control
  • Thermal control

The 500 year wall-Keep the water out of it. Allow the vapour to get out from the inside or outside if it gets in. Keep the air out of the wall from the outside and inside. Put all the thermal layers on the outside and put the cladding on the outside.

He also analyses the LEED energy standard.

To Vent or not to Vent (Roofs-cold, warm and SIPS)

This video covers venting and airtightness of SIP roofs.

What happens when one uses a white roof membrane versus a black one.

Building Enclosures

Why increasing insulation is a game changer in the future . Moisture and durability issues that lie ahead because of extra insulation.

 

Wall/Ceiling System

Wall/Ceiling  Electrical Services

For the internal wall build up I am using a double batten wall system. This wall system allows one to easily install services. In a previous experiment on building a workshop (used as a means to experiment on a small building before commencing the house) I installed a single row of horizontal battens on the OSB board. This made it very difficult to run services that need to run vertically. I had to install metal protecting plates and cut notches in the wood in order to ensure that I did not damage wiring due to the final layer of plasterboard screw fixing.

When one uses a counter batten system it facilitates running services such as power,  lighting, phone, internet, alarm etc without the risk of screw damage. This system also helps to reduce the cost of installing these services (see the image of a cable behind the batten below).

One can make use of a wall system like this if a soft insulation such as cellulose or fiberglass is behind the final batten which will support the plasterboard finish.

Wall Cable Routes
A row of battens run vertically behind the membrane in order to facilitate running services.

When working at ceiling level one may need to use a counter batten system in order to allow for recessed lighting otherwise it will mean installing special electrical enclosures cut into the airtight membrane. I have installed counter battens to a depth of approximately 90mm in the living and kitchen areas for LED downlights (see the previous post link on the 26/04/2015). In the bedroom areas I will only use a single batten system in order to install hanging pendent fittings.

Floor Level Insulation.

At floor level I installed Rockwool insulation for two reasons -one was to minimise the thermal bridging (heat loss around the wooden sole plate that the timber wall sits on) and the second reason was to minimise the damage to the insulation if there was a water leak.

I carried out a test where I placed 50mm of Rockwool RWA45  (product in the left bowl) and Metac (fiberglass-product in the right bowl below) in water in order to see what would happen if there was a leak. The Rockwool absorbs very little water but the fiberglass sank and became completely saturated and would possibly never dry out. Both insulation’s were submerged initially and then left for the duration of the test.

Rockwool Metac
Rockwool versus Fibreglass for water damage.

Below is an image of the Rockwool installed at floor level under the fibreglass in order to minimise the risk of insulation damage at floor level and minimise thermal bridging.

Rockwool
Rockwool Installed at Floor Level (green colour)

Airtight Membrane Installation

When installing the airtight membrane I was surprised how quickly the knife goes blunt. Rather than using the disposable knives and blades I now use a sharpener with the knife.

Knife and Sharpner

Passive House Exterior Cladding

Exterior Cladding Decision

There were a number of choices when it came to the exterior cladding.  Because the house is a timber frame I went for a ventilated facade with cement boards. The decision for selecting this was based on the following:

  • Because the house is highly insulated very little heat will travel through the wall structure. This entailed changing the wall build-up on the advice of our timber structural engineer. On a normal timber frame one installs a rigid OSB board on the outside and this then would typically be covered with a membrane and then battened for the cement board or tied to block work. When the timber structural engineer carried out a Wufi analysis (hygrothermal analysis-how the wall behaves with our humidity levels in Ireland) he advised that the structural strength of the OSB board would be affected if we placed it outside because of moisture build up. The OSB was then placed inside with only the vapor barrier on the outside and then the outside was battened /counter battened for the cement board.
  • My preference was to use block work on the outside (because of cost advantage) but this showed up in Wufi as needing large amount of ventilation and it would not perform as well as a cement board or a wood finish wall.  It seems that if one used block work the heat from the sun would take a long time to reach the ventilated space. The ventilated space it appears requires two pieces of physics to work correctly-Thermal Buoyancy (warm air rising and creating a drying out environment)  and Wind for the ventilated cavity. Relying on one of these I felt was a risk I did not want to take.
  • The other reason for selecting a ventilated cavity versus using an externally insulated (with a non breathable product) was the provision of a second level of protection to the wall structure if there was a fault in the external waterproofing . If for example water leaked in around a window detail it would dry out if the wall was ventilated but if water got in behind a wall that was externally insulated with Polystrene/EPS/PIR/PU  the opportunity to dry out was I felt limited.

By selecting a cement board (around 12mm thickness) if the sun shines on this  it would within a very short period of time let the heat transfer to the inside of the ventilated cavity and increase the drying out of the wall and also keep the insulation dry so that it can perform at its rated value.

Some Details

The membrane was glued around the external structure of the timber frame and wall to ensure that no wind would be blowing over the face of the insulation ie. Minimise thermal looping.

Orcon F membrane
Membrane glued with Orcon F to concrete and wood structure

 

 

 

 

 

 

 

 

 

 

 

The membrane was placed over the Insulation and glued to structure as seen above.

Metac Insulation, Passive House
220mm Metac Insulation placed between external structure before membrane applied.

 

 

 

 

 

 

 

 

 

 

 

External Membrane applied over Insulation

Solitex WA
Membrane covering Insulation

 

 

 

 

 

 

 

 

 

 

 

Battens for Cement Board Cladding

Preparation for Cement Board Cladding
Counter Battens On Window Walls

 

 

 

 

 

 

 

 

 

 

 

Aluminium ventilation vents for walls.

Wall ventilation for exterior Cladding
Aluminium Ventilation Grille

 

 

 

 

 

 

 

 

 

 

 

Cement Board sample

Cement Board

Cement Board Sample

The Cement Board is screwed onto the battens with stainless steel screws. A base coat and mesh is applied first and then a primer. The final finish is a Ral colour acrylic render to make the cladding water proof. If one has a walls facing south west and they are subjected to high rainfall it may be better to install a Silicone Silicate render or check that a chemical agent is included to reduce/eliminate algae growth that can appear as a green discoloration on the render over time.

Acrylic Render
Acrylic Render Finish

The overhang underside was also clad with an acrylic render.  The image below shows the overhangs shading the top windows. For example by around 9:30 AM in June the top windows are completely shaded for the sun and by 14:30 all the lower windows are in shade in order to protect the building from overheating.

Inter-connector between two buildings with 1.8m Overhangs.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Wall Battens, Air Tightness, Service cavity and Plasterboard

Wall Battens

I have started preparing the internal walls for more insulation, air-tightness and the service cavity .

Isover Metac Insulation
First Wall with 50MM Metac insulation between vertical battens

There appear to be no hard and fast rules on mounting the battens and counter battens . Below are the Gyproc guidlines:

“Horizontal application of plasterboard on walls is generally
   recommended because it:
• Reduces joints by up to 25%.
• Provides a stronger wall.
• Reduces the possibility of unacceptable light reflections
around joints.
• Joints are at a more convenient height for finishing.

However, the orientation should be chosen so that – any
critical light falls along the recessed joints; the number of butt joints is minimised; a single sheet may be fixed vertically where it covers the whole wall. Nogging is not required behind recessed edge joints in horizontal applications. Partitioning fixed to steel framing in commercial applications is typically sheeted vertically. The lower edge of wall sheets is to be kept a minimum 6mm above the finished floor level. Ceiling sheets are to be installed with the long edge at right angles to the direction of the joists/main support members.”

The important factor is batten spacing . A good spacing it apears is 400mm for the plaster board. I am installing the first row of battens vertically at 600 centres. These will carry the next row of battens for the plaster board at 400 centres. I am placing the final row of battens horizontally in order to facilitate wiring and services. Fixing the plasterboard with screws appears to be better than using nails (Nº6 Type ‘W’ for timber framing a different screw type is required for other systems.)

Passive House Wall Build up
Wall Membrane and Airtight Layer with Battens

I used screws and serrated nails on the vertical battens. This layer of vertical battens will hold the 50mm metac insulation (see above and below). Next will be the airtight membrane followed by the horizontal battens. I will be placing 15 mm plaster board on the inside walls and ceiling and I am considering some other suitable board like a magnesium board (Mgo).

All the north facing walls will have cupboards/wardrobes placed in front of them. It allows me to practise knowing that they will not be seen again. I am also considering mounting the plaster board vertically on these walls as it will take one sheet exactly (2.4metre high).

Thermal Bridging at Sole Plate

Rockwool at Floor Level to minimise thermal bridging

Service Cavity

A small length of the lower floor section in the kitchen will have a service route specifically for pipes and wiring behind the skirting board. (I want some way of accessing these in the future without taking the wall apart .)

Insulation at floor level

At the floor level where the sole plate sits on the structural ring beam I am placing rockwool in order to reduce the heat loss (thermal bridge). It appears that rockwool has superior fire resistance-I must do a test this week and see for myself.

Passive House WallWall Layers with Insulation

Above is a sketch of the wall build showing the basic components. For passive house certification I need to calculate the thermal bridge losses (linear heat loss) at this floor/wall junction. If I did not apply the rockwool insulation I would have significant heat losses and possibly condensation issues. I will calculate the thermal bridge losses using the free Therm software. It will show the real performance heat losses and condensation risks if any.

Insulation

Insulation

As the building is a wooden frame structure the choice of insulation was limited. Cellulose ( K value around 0.039 W/mK ) was the preferred option but I opted for Isover Metac semi rigid insulation with a K value of 0.034 W/mK in order to keep the wall thickness to a minimum (currently 430 mm including a service cavity giving a U value of 0.09 W/(m²K) and to be able to do some of the work myself.

The roof U value is 0.102 W/(m²K) and the thickness is 530 mm  with 400 mm of Metac. Other insulating options were wood fibre board, sheep’s wool but the cost of theses was prohibitive in our build. A good explanation of these technical values can be found at the Rockwool Basic Theory link Insulation terms.

When insulating the wall structures (whether it is block-work, straw, hemp,wood etc) one is always trying to work out what could go wrong if some part of the building fabric failed and how would it correct itself if it goes wrong. A wall structure that is capable of drying out in the Irish Climate is the goal. What might work in Germany or another country may not work in Ireland.

In our build I considered using block work outside the wooden frame because of the lower cost. It turned out after a Hygrothermal analysis with Wufi that there was a greater potential for the wall not to dry out over certain seasons because of the amount of insulation in the walls limiting the thermal buoyancy that primarily assists air to circulate in a cavity. The more insulation that is placed in a wall the less heat can escape to dry out the wall and create warm air that assists thermal buoyancy in the cavity. In our build we placed the OSB racking board inside the wall away from the external cavity because the structural engineer from my understanding advised that the increase in moisture could affect the structural integrity of the OSB as per his Wufi anlaysis. This potential risk was avoided rather than experiment with a worst case scenario.

One I feel has to plan for the worst case scenario. If I had used polystyrene or a PU/PIR insulation material in the wall I feel the risks would be greater in a wooden frame structure.

Fiberglass Samples

We tried a few different company samples of fiberglass and settled for the isover product Metac because the available sizes were compatible with the structure and the extra rigidity it appears to have when placed in the ceiling space ie.  it stays in place between rafters without any support. I initially thought at the planning/design stage I would need insulation netting on the ceiling but this was not necessary.

Metac Semi-rigid shown on the left. Knauf on the right.
Metac Semi-rigid shown on the left. Knauf on the right.

 

 

 

 

 

 

 

 

 

 

 

Strategy to deal with Fibreglass

The installation strategy I chose for the insulation was that no fiberglass product would be used inside the airtight membrane for sound proofing or insulating purposes in order to minimise fibers in the air.  A name I have given this is the zoo approach (keep the fibers behind the airtight membrane like in a zoo where the animals are behind the glass).

When cutting the insulation it needs an extra 10-20mm in order to ensure that it fits perfectly otherwise extra effort is required to place it in position. This is a very small tolerance when cutting a circular roll of insulation of 550mm diameter.

Tools

The existing tools I came across for cutting the fiberglass were as follows:

  • The standard wood saw
  • Insulation Saw (creates a very clean cut with minimum fibers in the air but it has difficulty cutting through the plastic cover of the insulation)-
    Insulation Saw
    Manual Insulation Saw

     

  • Electric Insulation saw (I did not buy one but this is what one looks like.)  –
Insulation
Dewalt Electric Insulation Saw DWE 397

 

  • Hand knives such as Stanley knives.

I could not find any tool that I could hire to cut the insulation in order to improve the accuracy of the cut nor speed up and simplify the installation. I tried a few ideas myself from a mechanical saw with senior hacksaw blades to an automatic tool I put together. I will return and develop a tool from what I have learned.

  • Home made tool-my preference was to use this tool I put together which was made up of 3 hacksaw blades. It allows one to roll the insulation on the floor and cut it as it is rolled.

    Insulation saw
    Home made saw with  hacksaw blades.

 Protective Equipment

I tried numerous dust masks and the one I settled for was the 3M 9322+

3M 9322+
Masks Tested-Prefered the 3M 9322+ Mask

The other ones got too warm, did not keep out the insulation or caused the goggles to fog up.

When working on the ceiling a full visor mask worked out the best.